From the idea to the project: Planning and construction of the first school block with two classrooms
Construction of a round hut for the school administration
Building of a second school block with two classrooms and sectors for administrative purposes and storage
Construction of a second round hut for the teachers and other staff members of the school
Construction of a new toilet facility with 4 toilet rooms
Building of new a kitchen for the school
Opening of the Nursery school (first block) with three classes K1, K2, and K3
K3 children had to be taught for some time in the round hut, which was originally planned for the school administration. About 80 children in the Nursery School attended in the first academic year.
26 children (the first group of K3) successfully completed their Nursery School such that they could start as proud P1 pupils their next academic year in February 2015 in the newly built primary school block.
After the completion of the second school block, the 1st class of the primary school P1 was opened in February 2015 with 26 children.
All children of nursery-and primary schools receive lessons between 8:00 to 16:00 hours. Breakfast and lunch are provided for the school pupils. The pupils are taught by professional teachers. As always the case is, and this is common practice and according educational system in Uganda, the kids wear school uniforms.